Welcome to the PoE Texas Manual for the 56 volt 3000 watt managed power supply for building infrastructure!
The purpose of the manual is to help you quickly and effectively navigate the installation and functions of your new Power Over Ethernet Power Supply.
Our goal is to make our products as intuitive and simple to use as possible, so we value your feedback and questions directly to us at service@poetexas.com. Phone +1-512-479-0317.
Or you’re always welcome to leave questions or comments on our product page: PS-53v3000w.
What’s Inside
General Installation
Your new PoE injector is designed to be simple to install and set up. You should only need at most a Philips head screw driver and a patch cable for the management console.
NOTE: The injector includes the screws for the rack wings, but it does not include the rack mounting nuts or screws. So, you’ll want to grab some of those.
Rack Installation
The power supply comes pre-assembled with brackets for a 19″ rack configuration. Please contact us if you need a different rack. It DOES NOT come with the nuts and screws to mount the injector onto the rack. You’ll need to get those.
Wiring the Power Supply
WARNING: THIS INVOLVES WIRING AC POWER AND SHOULD BE PERFORMED BY A QUALIFIED PROFESSIONAL.
SELECTING THE POWER SOURCE: This power supply can draw more than 2,000 watts of power. A typical 15 amp, 120 VAC circuit breaker will trip at 1,800 watts. If you just plug it into a regular 15 amp circuit with other lights and outlets, it will draw enough power to trip the breaker. For a full lighting application, it requires a dedicated 20 amp circuit.
STEPS:
- Ensure power is properly disconnected from the wiring to the device
This may mean either keeping the included AC cable unplugged or shutting off the breaker to the circuit.
- Connect the AC power to the AC input.
“L” is typically a black wire
“N” is typically a wire wire
Ground is typically green
Tip: Use a small, flat head screw driver inserted into the small square hole to “open” the push-in connector before inserting the cable. Once the cable is pushed all the way in, remove the screw driver to clamp onto the cable. Test the connection by gently tugging the wiring.
Don’t forget to ground the cable and the power supply.
Now you can wire the DC side of the power supply.
DO NOT CONNECT POWER TO THE DEVICE YET.
What do you do with a 3,000 watt 48-56 volt managed power supply?
You power the PoE Texas 24 port Layer 2 PoE++ switch for lighting and automation: GBTS-28-24-M (See wiring)
Configuration
You can configure the PS-53v3000w either through screen and controls on the device, though a webpage management tool, or even through an SNMP interface.
In this manual we’ll cover the details for the on-screen and web interface. If you’d like to see the manual for the other configuration methods, you can find it here:
SUPER TECH MANUAL – PS-53v3000w
In this manual we’ll demonstrate how to navigate the onscreen and web interface to be able to:
- Monitor the status of the device
- Adjust the output voltage
- Change the device passwords
- Change the device ID
- Change the device Date and Time
- Change the IP address
Operating The LCD Screen
Change the Charge and Output Voltage
Follow these steps:
Click the return button to enter the Menu ↵
Right arrow to navigate to Settings →
Return button to enter the Menu ↵
Return button to enter the Password ↵
Return button to enter Batt Settings ↵
Up arrow to navigate to Charge Settings ↑
Return button to enter Charge Settings ↵
Return button to edit ↵
Right arrow to navigate to Place Holder →
Up arrow to change settings ↑
Back arrow when finished ⊂
View Status
Simply click the right arrow (>) to scroll through:
Main Display – Date, Volt In, Volt Out, and Total Load
Battery Status
Temperature – Battery and Ambient
Inverter Status – Not used in this configuration
Alarm Status – Inverter (not used) and System Status
Change the System Configuration:
Follow these steps:
Click the return button to enter the Menu ↵
Right arrow to navigate to Settings →
Return button to enter the Menu ↵
Return button to enter the Password ↵
Right arrow twice to navigate to Settings → →
Return button to enter the Sys Settings ↵
Up arrow to change password to 1000 ↑
Return button to enter the Password ↵
To Change the Passwords:
Right arrow to select Password 1 →
Right arrow twice to select Password 2 → →
Up arrow to select the password ↑
Return button to edit ↵
Use th up and right arrows to edit ↑ →
Return button to finish ↵
Back to Sys Settings ⊂
Right arrow to navigate to Date →
Up arrow to change settings ↑
Back arrow when finished ⊂
Web Management
CONNECTING TO THE CONSOLE
The PS-53v3000w has a web-based management interface that can be accessed through the console port on the front of the power supply. Before you integrate it into your network, you will need to configure the device such as setting the date and time, IP address, and username and passwords.
First you need to connect the console port on the front of the power supply to a computer. If you don’t have an ethernet port on your laptop, this works just fine with an ethernet to USB adapter.Then power on the power supply. The settings will remain in the device even if you power it off and power it on again.
Now comes the techiest part of the process. You will need to disconnect your computer for wifi and the internet. I know this feels very dangerous, but it’s only for a moment.
I’m giving the instructions here for a Windows computer. If you need help doing this on a MAC, simply go to YouTube and search on setting an fixed IP address for a MAC. Then use the IP address information I give below.
In Windows, navigate to your Network and Sharing Center. If you don’t know how to get there, simply click on the Window button on the bottom left and type “Network and Sharing Center”.
When it comes up, you should see an ethernet connection. If not, double check 1) you’re connected to the injector, and 2) the injector is powered on.Click on the ethernet connection. It will bring up a dialog box.Click “Properties” on the bottom left.
In the next dialog box, look in the middle for “Internet Protocol Version 4”. Click on it, then click “Properties” in the bottom right.
Fill out the fields just like this.
Click: User the following IP address
IP Address: 192.168.1.20
Subnet Mask: Sets itself
Default Gateway: 192.168.1.1
Preferred DNS Server: 8.8.8.8
Alternate DNS Server: 4.2.2.2
Hit Okay to close this dialog, then Okay one more time.
I’ve tried not hitting okay the second time, and I couldn’t get it to connect. So, make sure it hit okay to close out the two dialogs.
Then navigate to 192.168.1.190.
The video below will take you through the rest of the configuration.
Depending on your model, your username and password maybe different. If the password in the video does not work, please try this default username and password:
Username: admin
Password: password
Heat Load Calculator
The PS-53v3000w does put off enough heat when under load that it’s important to consider how you will deal with the heat. The key considerations are:
- The PS-53v3000w operates well up to 55 C or 131 F in local ambient conditions
- Local ambient conditions mean the space where the power supply will be located
- While an office space may be at 75 F, a fully enclosed rack without ventilation can easily go above 130 F
- Ideally the PS-53v3000w is installed in the rack with at least 1u space between it and the GBTS-28-24-M
- Racks should either be open in the back or have good, reliable forced ventilation to move around around and out of the cabinet
- The room outside, typically an IDF or MDF, the rack or cabinet should have local temperature control through a thermostat and air handling unit
- See the Heat Load Calculator to see how to size any air handling or air conditioning requirements
To estimate the heat load of the GBTS-28-24-M power supply, visit that Heat Load Calculator.
Technical Specifications
Product Specifications
AC Plug Connector Type | Spring Cage Clamp 12 AWG |
Adapter length | 3 ft |
Cable connector length | 2 ft |
Certifications | CE, FCC, UL |
Dimensions | 19 x 13 1/4 x 1 3/4 in |
Display Type | LCD |
Efficiency | >90% at full load |
Input Frequency Range | 45 – 65 Hz |
Input Voltage Range | 85-290 VAC |
Management Port | 1 |
Max Current | 40 amp |
Max Power for Kit | 6000 watts at 200 VAC, 3000 watts at 120 VAC |
Max Voltage | 42-58 volt DC |
Mount Type | Rack |
Operating Temperature Range | -40 – 55 degrees C |
Output Voltage | 53 Volts |
Power Supplies | Hot Swappable Dual Rectifiers |
Weight | 13 lbs 12.2 oz |